Saturday, March 12, 2011

Kitchen Wall, Insulation and Strapping

The insulation and strapping is now complete over the entire house, including the newly completed south kitchen wall. Next will be the roof, windows and doors and interior partitions. Once the interior partitions are framed the plumber can come back and then electrician can start. 


South kitchen wall. Not a bad view!
This time including the windows on the west side as well.